Subfloor preparation

Every floor is only as good as what is under it. Flat, dry, clean and firm.

Flat

Lay a 2 m straightedge (or long spirit level) across the floor in several directions. Measure the largest gap under it.

Grind or sand high spots. Fill hollows with a self-levelling compound after priming. Small dips can be filled with a trowel-applied repair mortar.

Dry

New sand-cement screed dries slowly: a rough rule is a week per centimetre for the first 4 cm, and much longer beyond. Test it with a moisture meter or a CM test before laying wood or laminate. Anhydrite (calcium sulphate) screeds have much stricter limits than cement screeds.

On concrete and screed, a floating floor needs a vapour barrier: PE foil, usually 0.15–0.2 mm (6–8 mil) as the floor maker specifies, with 20 cm overlaps, taped and turned up at the walls. For timber subfloors, do not use plastic foil; check the moisture of the boards instead. Under wood flooring over an unheated space, NWFA allows a Class II retarder such as #15 felt; over a heated room at the same conditions, none is needed.

Clean and firm

Remove old adhesive ridges, nails and staples. Screw down any creaking timber boards. Vacuum thoroughly; grit under a floating floor causes squeaks.

Old floors underneath

Many floating floors can go over existing tiles if they are firm and flat; fill wide grout lines. Never lay over carpet or soft vinyl.

Wood flooring guidance on this page follows the NWFA Wood Flooring Installation Guidelines (2025 edition) from the US National Wood Flooring Association, written for North America. In Europe, national codes apply instead, such as BS 8201 in the UK and DIN 18356 in Germany, and climate ranges often differ. Your flooring maker's instructions come first: if they say something different, follow them.